WBS # Name / Title Type Start Date End Date
1 Youth Empowerment Sanctuary project 11/9/2020 10/25/2024
1.1 Programs group 11/9/2020 10/25/2024
1.1.1 Education for LAP task 11/30/2020 12/2/2020
1.1.2 Mentorship of 20 hours task 11/9/2020 12/18/2020
1.1.3 Association with State task 12/8/2020 12/8/2020
1.1.4 Test for National drug & alcohol counselor task 12/16/2020 1/26/2021
1.1.5 Course & test for Substance abuse professional task 1/19/2021 3/15/2021
1.1.6 OC youth employment buy equipment & deliver task 5/28/2021 7/8/2021
1.1.7 OC youth employment raw material produced task 7/12/2021 9/30/2021
1.1.8 OC youth employment connections (school of forestry, construction, mill task 10/4/2021 10/25/2024
1.1.9 OC Substance abuse counseling task 10/4/2021 10/25/2024
1.1.10 OC SUD questionnaire (twice a year) task 10/4/2021 10/25/2024
1.2 Planning and Approval group 1/4/2021 6/2/2021
1.2.1 Three formal bids task 1/4/2021 2/1/2021
1.2.2 Oregon City committee approval subgroup 2/9/2021 2/26/2021
1.2.2.1 Oregon City committee approval task 2/9/2021 2/26/2021
1.2.3 US Bank approval and paperwork task 2/26/2021 4/8/2021
1.2.4 Finish Design based on permit approval task 4/27/2021 6/2/2021
1.2.5 Build Barn for temporary storage and future activities task 4/27/2021 6/2/2021
1.3 Construction group 6/2/2021 12/28/2021
1.3.1 Mobilization task 6/2/2021 6/4/2021
1.3.2 excavation task 6/7/2021 6/25/2021
1.3.3 Foundation for Community & 1st hut task 6/17/2021 7/28/2021
1.3.4 Preparing raw materials for expansion task 7/15/2021 8/25/2021
1.3.5 Permit approval on foundation task 8/26/2021 8/30/2021
1.3.6 Rough framing task 8/31/2021 9/28/2021
1.3.7 Structural & sepic task 9/29/2021 10/14/2021
1.3.8 Inspection: Framing milestone 10/18/2021 10/18/2021
1.3.9 MEP rough-in task 10/20/2021 10/25/2021
1.3.10 Inspection: MEP rough-in milestone 10/27/2021 10/27/2021
1.3.11 Drywall task 10/26/2021 10/29/2021
1.3.12 Painting task 10/25/2021 10/28/2021
1.3.13 Trim task 10/27/2021 12/7/2021
1.3.14 Finishes/fixtures task 11/22/2021 12/28/2021
1.3.15 Substantial completion milestone 12/27/2021 12/27/2021
1.4 Closeout group 12/29/2021 1/14/2022
1.4.1 Punch list task 12/29/2021 1/7/2022
1.4.2 Final inspections milestone 1/11/2022 1/11/2022
1.4.3 Closeout documents task 1/13/2022 1/14/2022
1.5 2nd Unit for youth housing group 1/3/2022 7/29/2022
1.5.1 start framing kits task 1/3/2022 4/29/2022
1.5.2 Foundation pad for 2nd unit task 5/2/2022 5/31/2022
1.5.3 Assemble kits task 6/1/2022 7/29/2022
1.6 Rehab for substance abuse group 8/31/2022 2/28/2023
1.6.1 funding for rehab facility task 8/31/2022 11/24/2022
1.6.2 State of Oregon cred. for rehab task 1/4/2023 2/28/2023